Structure Repair | Specialized on pier structural member repair, dimensional and positional repair, off-shore structure repair, Survey/Inspection.
Holcim Philippines - Luga-it, Misamis Oriental |
September 14, 2006 - October 19, 2006
FLED/DiveCenter Project:
- Pier head fender cluster piles underwater cleaning and inspection at old pier.
- Mobilization, hauling of materials, miscellaneous tools, equipment and underwater safety gadgets from warehouse plant premises to job site.
- Verification of actual locations, dimensions and measurements at site prior to commencing of the cluster piles cleaning activity.
- Removal or cleaning of marine deposits, barnacles, grease, oil and other contaminants on the four elevations of cluster piles above and below water from pier approach and entire of pier head.
- Preparation and submission of detailed reports of the cleaning and inspection of cluster piles photography in four elevations of the cluster piles showing defects.
COMMENTS